Fish Creek Atlantic Salmon Club Comings and Goings

We have had a busy fall working on our hatchery at the Harden dam site in McConnellsville this year.  The modifications made to our hatchery equipment and the building itself should provide a safer environment for this up-coming year’s eggs:

Our tank #3 hinged cover was removed and the tank modified to be   like our tanks 1 & 2.

Tank stabalizing systems have been installed on all 3 tanks to   prevent tipping if flooding should happen again; tanks should float up, if   water floods the hatchery.

Insulation has been installed to reduced heat losses from the   hatchery during freezing weather.

Insulation has been installed to all 3 tanks.

Piping to each tank has been installed and supported as   needed.

Hurricane tabs have been installed as required by our building   design.

The roof is in the process of being finished; one more work day   this Friday should finish that; if you are able to help, please respond by   return e-mail.

 

Respectfully submitted,

Arley Morey, Club Secretary